Fiscal Year 2019-2020 Pavement Rehabilitation (Slurry Seal) Project

Post Date:07/30/2019

Fiscal Year 2019-2020 Pavement Rehabilitation (Slurry Seal) Project

Pavement Coatings Company will be performing street pavement repairs during the month of August 2019. The scope of work includes pavement removal and replacement, pavement crack sealing, and installation of slurry seal. Notices and door hangers will be used to inform ALL affected residents. Please observe the “No Parking” signs that will be posted in advance of the work activities. The affected streets will have closed to traffic until the new surface sets and is ready for traffic. Below is the Contractor’s breakdown of weekly activities:

8/1 to 8/2 Localized Pavement Remove and Replace
8/5 to 8/9 Existing striping removal and crack sealing.
8/12 to 8/16 Slurry Seal Material installed & cat tracking for striping of new surface.
8/19 to 8/21 Striping first coat.
8/26 to 8/28 Striping second coat.